BH0-010 · Question #160
Scenario 7 "Test Estimation" You have been contracted to manage the acceptance testing of a new computer-based reservation system for a travel agency. You have provided an approximate budget…
The correct answer is D. Unknown input quality due to third party development. See the full explanation below for the reasoning.
Question
Scenario 7 "Test Estimation" You have been contracted to manage the acceptance testing of a new computer-based reservation system for a travel agency. You have provided an approximate budget estimate for the testing project based on previous experience with similar sized projects. However, the management of the parent company of the travel agency will not commit to the budget until detailed cost estimates are provided. The reservation system is being developed by a third party However, detailed specifications of the software are available, as well as an estimate of the total effort that will be spent in developing the software. The software is to be delivered in four increments, and the functionality to be delivered in each increment has already been agreed on. Which aspect in the test estimate is the main risk in this project? 1 credit
Options
- AQuality of the specification
- BAvailability of end-users
- CThe costs of hardware and tools
- DUnknown input quality due to third party development
How the community answered
(31 responses)- A6% (2)
- B3% (1)
- C10% (3)
- D81% (25)