When should testers be involved in reviewing a UAT specification? [K1]

The correct answer is C. As soon as the UAT specification has been drafted. See the full explanation below for the reasoning.

Question

When should testers be involved in reviewing a UAT specification? [K1]

Options

  • AAt the beginning of the project
  • BAs soon as requirements have been approved
  • CAs soon as the UAT specification has been drafted
  • DAt any time before UAT begins

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    11% (4)
  • C
    71% (27)
  • D
    13% (5)