nerdexam
BCS-ISEB

BH0-010 · Question #364

Which of the following risks represents the highest level of risk to the project?

The correct answer is B. Likelihood of failure = 10%, potential cost of impact = $500,000. See the full explanation below for the reasoning.

Question

Which of the following risks represents the highest level of risk to the project?

Options

  • ALikelihood of failure = 1%, potential cost of impact = $1m.
  • BLikelihood of failure = 10%, potential cost of impact = $500,000.
  • CLikelihood of failure = 20%, potential cost of impact = $150,000.
  • DLikelihood of failure = 5%, potential cost of impact = $500,000.

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    75% (18)
  • C
    4% (1)
  • D
    13% (3)

Community Discussion

No community discussion yet for this question.

Full BH0-010 Practice