BH0-010 · Question #350

What is the main reason for using a pilot project to introduce a testing tool into an organization? [K1]

The correct answer is C. To assess whether the tool will be cost- effective. See the full explanation below for the reasoning.

Question

What is the main reason for using a pilot project to introduce a testing tool into an organization? [K1]

Options

  • ATo identify the requirements for using a tool
  • BTo make a selection between alternative tools
  • CTo assess whether the tool will be cost- effective
  • DTo ensure the tools fits existing processes without change

How the community answered

(65 responses)
  • A
    3% (2)
  • B
    6% (4)
  • C
    78% (51)
  • D
    12% (8)