Important consequences of the impossibility of complete testing are:
The correct answer is D. All of the above. See the full explanation below for the reasoning.
Question
Important consequences of the impossibility of complete testing are:
Options
- AWe can never be certain that the program is bug free.
- BWe have no definite stopping point for testing, which makes it easier for some managers to argue
- CWe have no easy answer for what testing tasks should always be required, because every task
- DAll of the above
How the community answered
(26 responses)- A12% (3)
- B8% (2)
- C4% (1)
- D77% (20)