Which of the following is not decided in the test-planning phase..?
The correct answer is D. Types of test cases. See the full explanation below for the reasoning.
Question
Which of the following is not decided in the test-planning phase..?
Options
- ASchedules and deliverables
- BHardware and software
- CEntry and exit criteria
- DTypes of test cases
How the community answered
(32 responses)- A9% (3)
- B3% (1)
- C3% (1)
- D84% (27)
Community Discussion