Which of the following is not decided in the test-planning phase..?

The correct answer is D. Types of test cases. See the full explanation below for the reasoning.

Question

Which of the following is not decided in the test-planning phase..?

Options

  • ASchedules and deliverables
  • BHardware and software
  • CEntry and exit criteria
  • DTypes of test cases

How the community answered

(32 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    84% (27)