The cost of fixing a fault:
The correct answer is B. Increases as we move the product towards live use. See the full explanation below for the reasoning.
Question
The cost of fixing a fault:
Options
- AIs not important
- BIncreases as we move the product towards live use
- CDecreases as we move the product towards live use
- DIs more expensive if found in requirements than functional design
- ECan never be determined
How the community answered
(56 responses)- A4% (2)
- B73% (41)
- C5% (3)
- D16% (9)
- E2% (1)