nerdexam
BCS-ISEB

BH0-010 · Question #175

The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the…

The correct answer is D. The bidder's project test plan depicts a phased implementation with later delivery dates to be. See the full explanation below for the reasoning.

Question

The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate? 2 credits

Options

  • AThe bidder's test policy should enforce that incident management fully conforms to IEEE 1044.
  • BThe bidder's project strategy shows that the data content of all the test environments conforms to
  • CThe bidder's test plan shows that the application will be delivered for acceptance in six months
  • DThe bidder's project test plan depicts a phased implementation with later delivery dates to be

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    11% (4)
  • D
    82% (31)

Community Discussion

No community discussion yet for this question.

Full BH0-010 Practice