Scenario 8, V2 "Test Proems Improvement' You have raised the issue that improving the testing process is also dependent on the status of the software development process. Which of the following…
The correct answer is D. Test project closure. See the full explanation below for the reasoning.
Question
Scenario 8, V2 "Test Proems Improvement' You have raised the issue that improving the testing process is also dependent on the status of the software development process. Which of the following phases in the fundamental test process is considered to deliver a document which can be used as a major input for test process improvement? 1 credit
Options
- ATest planning and control
- BTest implementation & execution
- CEvaluating exit criteria and reporting
- DTest project closure
How the community answered
(27 responses)- A11% (3)
- B4% (1)
- C7% (2)
- D78% (21)