BH0-010 · Question #141

Scenario 4, V2 "Test Management Tool" The project situation after 11 months is: - The first increment was released one week late but contained sufficient functionality to be declared fit for…

The correct answer is C. Arranging a back-up test environment in case the existing one fails during testing. See the full explanation below for the reasoning.

Question

Scenario 4, V2 "Test Management Tool" The project situation after 11 months is:

  • The first increment was released one week late but contained

sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.

  • The amount of voluntary overtime worked PV the test team has reduced

the second Increment slippage to just 3 weeks.

  • There is talk of reducing the scope of requirements. The purpose of

this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).

  • Concerns have been expressed by a section of the user community, that

in some places the usability is very poor. Which of the following is a project risk mitigation step you might take as test manager? 1 credit

Options

  • ATesting for performance problems
  • BHiring a contractor after a test analyst leaves the company
  • CArranging a back-up test environment in case the existing one fails during testing
  • DPerforming a project retrospective meeting using the test results after each increment

How the community answered

(49 responses)
  • A
    8% (4)
  • B
    2% (1)
  • C
    73% (36)
  • D
    16% (8)