At what point should capacity requirements of a proposed system be first considered?
The correct answer is B. As early as possible. See the full explanation below for the reasoning.
Question
At what point should capacity requirements of a proposed system be first considered?
Options
- ALeave it until the system is implemented and see if the system works O.K.
- BAs early as possible
- CWhen the Development Manager has completed testing and passes the system to Operations for
- DJust before the system goes live
How the community answered
(35 responses)- A9% (3)
- B83% (29)
- C3% (1)
- D6% (2)
Community Discussion