The correct answer is B. Ensuring that the accuracy of CMDB entries concerning software CIs is maintained. See the full explanation below for the reasoning.

Question

Which of the following is NOT the responsibility of the Release Management process?

Options

  • AThe physical aspects of software control
  • BEnsuring that the accuracy of CMDB entries concerning software CIs is maintained
  • CHelping to determine the software release policy
  • DDistributing software