AZ-400 Question #568: Real Exam Question with Answer & Explanation

The correct answer involves navigating to Project Settings > Pipelines > Settings > Retention and setting the artifact/symbol/attachment retention period to 60 days. This is the specific Azure DevOps configuration path that controls how long pipeline artifacts, symbols, and attac

Submitted by kev92· Mar 6, 2026Configure and manage Azure Pipelines - specifically managing pipeline settings including retention policies for build artifacts, symbols, and attachments within Azure DevOps project configuration.

Question

SIMULATION For Project1, you need to ensure that artifacts, symbols, and attachments are retained for 60 days. Answer:

Options

  • taskFor Project1, ensure that artifacts, symbols, and attachments are retained for 60 days by configuring retention policies.
  • prerequisitesAccess to Azure DevOps Project1

Explanation

The correct answer involves navigating to Project Settings > Pipelines > Settings > Retention and setting the artifact/symbol/attachment retention period to 60 days. This is the specific Azure DevOps configuration path that controls how long pipeline artifacts, symbols, and attachments are preserved before automatic deletion. Retention policies at the project level allow teams to balance storage costs with the need to access historical build outputs.

Topics

#Azure DevOps#Pipeline Retention Policies#Artifact Management#Project Settings