AZ-120 · Question #289

You have an on-premises SAP AnyDB deployment hosted on an operating system that is NOT supported in Azure. You need to migrate the deployment to Azure by performing a replatform and migration to SAP…

The correct answer is D. SAP Software Update Manager. SAP Software Update Manager (SUM) is correct because it includes the Database Migration Option (DMO), which combines a system update with a database migration in a single step - migrating from AnyDB to SAP HANA while also handling the OS/platform change (replatforming). This…

Migrate SAP workloads to Azure

Question

You have an on-premises SAP AnyDB deployment hosted on an operating system that is NOT supported in Azure. You need to migrate the deployment to Azure by performing a replatform and migration to SAP HANA. The solution must meet the following requirements:

  • Minimize administrative effort.
  • Minimize downtime.

What should you use?

Options

  • AAzure Migrate
  • BAzure Database Migration Service
  • CSAP Software Provisioning Manager
  • DSAP Software Update Manager

How the community answered

(61 responses)
  • A
    8% (5)
  • B
    15% (9)
  • C
    5% (3)
  • D
    72% (44)

Explanation

SAP Software Update Manager (SUM) is correct because it includes the Database Migration Option (DMO), which combines a system update with a database migration in a single step - migrating from AnyDB to SAP HANA while also handling the OS/platform change (replatforming). This minimizes both downtime (single-pass operation) and administrative effort (one tool, one process).

Why the distractors are wrong:

  • A. Azure Migrate - a tool for assessing and migrating VMs/servers to Azure, but it has no capability to perform a database-layer migration from AnyDB to SAP HANA.
  • B. Azure Database Migration Service - designed for Microsoft database engines (SQL Server, MySQL, PostgreSQL, etc.), not SAP workloads.
  • C. SAP Software Provisioning Manager (SWPM) - used for fresh SAP installations or system copies, but it requires a separate, manual database migration step, increasing effort and downtime compared to SUM DMO.

Memory tip: Think SUM = Single-step Update + Migration. The key phrase in the question is replatform AND migrate to HANA in one go with minimal downtime - that's exactly what SUM's DMO feature was built for. If you see "AnyDB → HANA" + "minimize downtime" together, SUM/DMO is almost always the answer.

Topics

#SAP Software Update Manager#AnyDB to HANA#replatform migration#minimize downtime