nerdexam
APMG-International

AGILEPM-PRACTITIONER · Question #47

AGILEPM-PRACTITIONER Question #47: Real Exam Question with Answer & Explanation

The correct answer is B. Check the Delivery Plan for deployment activities and update as required.. See the full explanation below for the reasoning.

Question

What action should the Project Manager take to plan the deployment activities?

Options

  • APrepare a Timebox Plan for the next Development Timebox.
  • BCheck the Delivery Plan for deployment activities and update as required.
  • CCreate a plan of activities to deploy the solution at the end of Timebox C.
  • DUpdate the Timebox Plan for Timebox C with the activities required to deploy the solution.

Community Discussion

No community discussion yet for this question.

Full AGILEPM-PRACTITIONER Practice