AGILEPM-PRACTITIONER · Question #47
What action should the Project Manager take to plan the deployment activities?
The correct answer is B. Check the Delivery Plan for deployment activities and update as required. In DSDM/AgilePM, the Delivery Plan is the project-level artifact that tracks all phases of the project lifecycle, including deployment - so the correct move is to consult and update it rather than create something new or put deployment into a Timebox Plan. Option B is correct…
Question
What action should the Project Manager take to plan the deployment activities?
Options
- APrepare a Timebox Plan for the next Development Timebox.
- BCheck the Delivery Plan for deployment activities and update as required.
- CCreate a plan of activities to deploy the solution at the end of Timebox C.
- DUpdate the Timebox Plan for Timebox C with the activities required to deploy the solution.
How the community answered
(23 responses)- A4% (1)
- B74% (17)
- C4% (1)
- D17% (4)
Explanation
In DSDM/AgilePM, the Delivery Plan is the project-level artifact that tracks all phases of the project lifecycle, including deployment - so the correct move is to consult and update it rather than create something new or put deployment into a Timebox Plan. Option B is correct because deployment is a project-level concern already scoped in the Delivery Plan, and the PM should update it to reflect the specific deployment activities rather than duplicating or ignoring existing planning artifacts.
A is wrong because a Timebox Plan for the next Development Timebox is forward-looking development planning, not deployment planning - these are different concerns at different levels. C is wrong because creating a brand-new plan ignores the Delivery Plan that already exists for this purpose; reinventing the wheel contradicts good governance. D is wrong because Timebox Plans govern work within a timebox (development activities), not what happens after it - deployment sits above the timebox level.
Memory tip: Think "Delivery Plan = big picture, Timebox Plan = sprint-level." Deployment is part of the big picture, so it lives in - and is updated via - the Delivery Plan.