AGILEPM-PRACTITIONER · Question #46

What action should the Project Manager take regarding the remaining windows?

The correct answer is D. Decompose the individual elements of work to be completed on the windows and reprioritise. Option D is correct because in Agile/DSDM frameworks, when work remains incomplete within a timebox, the proper response is to decompose the remaining work into smaller elements and reprioritize them against the backlog - ensuring the most valuable items are addressed first in…

Planning and Control

Question

What action should the Project Manager take regarding the remaining windows?

Options

  • AAll requirements that have not been met are automatically carried over to the next increment.
  • BExtend the time allocated to Timebox C, to allow time to complete these.
  • CInsist that all available resources within the Solution Development Team are redirected to this
  • DDecompose the individual elements of work to be completed on the windows and reprioritise

How the community answered

(32 responses)
  • A
    25% (8)
  • B
    16% (5)
  • C
    6% (2)
  • D
    53% (17)

Explanation

Option D is correct because in Agile/DSDM frameworks, when work remains incomplete within a timebox, the proper response is to decompose the remaining work into smaller elements and reprioritize them against the backlog - ensuring the most valuable items are addressed first in the next increment rather than blindly carrying everything forward.

Why the distractors are wrong:

  • A is wrong because unfinished requirements are not automatically carried over - they must be consciously reprioritized; assuming automatic carryover ignores the principle of prioritized delivery.
  • B is wrong because extending a timebox violates a core Agile/DSDM rule: timeboxes are fixed and should never be extended, as this undermines schedule discipline and predictability.
  • C is wrong because redirecting all resources to incomplete windows ignores prioritization - not all remaining work may be high-value, and doing so disrupts team balance without discriminating between what's worth completing.

Memory tip: Think of the timebox as a non-negotiable container - you can never stretch the box (no B), you must actively choose what goes in next (no A), and you don't brute-force everything in at once (no C). When something doesn't fit, you break it apart and pick the best pieces - that's D.

Topics

#requirement decomposition#MoSCoW reprioritization#Timebox planning#incremental delivery