AGILEPM-PRACTITIONER · Question #2
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility. Remember to limit your answers to the…
The correct answer is B. Enough description of the required refurbishment work should be provided to enable the C. During Feasibility, potential beneficiaries of the project should be involved when the Outline. In applying Agile Project Management to the creation of an Outline Business Case in support of the Feasibility Assessment, the following two statements are most appropriate: B . Enough description of the required refurbishment work should be provided to enable the Architecture…
Question
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility. Remember to limit your answers to the number of selections requested in each question. Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
Options
- AThe Feasibility Assessment should contain a detailed description of costs and benefits associated
- BEnough description of the required refurbishment work should be provided to enable the
- CDuring Feasibility, potential beneficiaries of the project should be involved when the Outline
- DThe Outline Business Case should demonstrate the mitigation of all business risks associated with
- EThe Outline Business Case should describe the full team structures to be engaged for the later
How the community answered
(49 responses)- A4% (2)
- B84% (41)
- D4% (2)
- E8% (4)
Explanation
In applying Agile Project Management to the creation of an Outline Business Case in support of the Feasibility Assessment, the following two statements are most appropriate: B . Enough description of the required refurbishment work should be provided to enable the Architecture Angels' Finance Director to decide whether the project should proceed. Agile approaches favor providing just enough detail to make informed decisions without going into unnecessary depth at early stages. This allows for flexibility and adaptation as more information becomes available. C . During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created. Agile methodologies emphasize stakeholder engagement and user involvement early and throughout the project. This ensures that the project delivers value and meets the needs of those it is intended to benefit.