AD0-E907 · Question #24
A team lead wants to identify overallocated resources within a project. Which report type would help achieve this?
The correct answer is A. Resource allocation report. A Resource Allocation Report is specifically designed to show how resources (people, equipment, etc.) are distributed across tasks and time periods, making it the go-to tool for spotting overallocation - where a resource is assigned more work than capacity allows. Why the…
Question
A team lead wants to identify overallocated resources within a project. Which report type would help achieve this?
Options
- AResource allocation report
- BAudit trail report
- CApproval status report
- DProofing report
How the community answered
(36 responses)- A72% (26)
- B3% (1)
- C17% (6)
- D8% (3)
Explanation
A Resource Allocation Report is specifically designed to show how resources (people, equipment, etc.) are distributed across tasks and time periods, making it the go-to tool for spotting overallocation - where a resource is assigned more work than capacity allows.
Why the distractors are wrong:
- B. Audit trail report - tracks changes and actions taken within a system for accountability purposes, not workload distribution.
- C. Approval status report - shows the state of items pending review or sign-off, unrelated to resource capacity.
- D. Proofing report - relates to reviewing and commenting on documents or assets, not resource scheduling.
Memory tip: Think "allocation = assignment." If you need to find who has too much assigned, you need the report that tracks assignments - the Resource Allocation Report. The word "overallocated" directly maps to "allocation" in the answer.