How does estimating a migration plan contribute to identifying potential risks in the migration process?

The correct answer is C. By creating contingency plans for identified risks. Estimating a migration plan forces teams to think through each phase in detail, and that structured thinking naturally surfaces unknowns and failure points - which leads directly to creating contingency plans (C) for those identified risks. A contingency plan is a pre-prepared…

Assessment and Planning

Question

How does estimating a migration plan contribute to identifying potential risks in the migration process?

Options

  • ABy generating reports on potential risks.
  • BBy allocating additional resources to mitigate risks.
  • CBy creating contingency plans for identified risks.
  • DBy automatically resolving identified risks.

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    3% (1)
  • C
    90% (26)

Explanation

Estimating a migration plan forces teams to think through each phase in detail, and that structured thinking naturally surfaces unknowns and failure points - which leads directly to creating contingency plans (C) for those identified risks. A contingency plan is a pre-prepared response if a risk materializes, which is the direct output of the estimation/risk-identification process.

Why the distractors are wrong:

  • A is wrong because estimation doesn't generate reports - risk reporting is a communication activity, not an outcome of estimation itself.
  • B is wrong because allocating resources is a response to risks already known, not part of identifying them during estimation.
  • D is wrong because estimation is a planning activity - it can never automatically resolve risks; resolution requires actual execution and decision-making.

Memory tip: Think of estimation as a rehearsal - when you mentally "walk through" the migration step by step, you spot where things could go wrong and write a backup plan (contingency) for each one. Estimate → Identify → Contingency is the logical chain.

Topics

#Risk Identification#Migration Planning#Contingency Planning#Estimation