A client is experiencing failed Business Processes (BP) due to a resource group not having an active adapter available. Which menu path identifies the adapters that are disabled?

The correct answer is C. Deployment > Services > Configuration > List. See the full explanation below for the reasoning.

Question

A client is experiencing failed Business Processes (BP) due to a resource group not having an active adapter available. Which menu path identifies the adapters that are disabled?

Options

  • AOperations > Thread Monitor
  • BOperations > Support Tools > Support Case
  • CDeployment > Services > Configuration > List
  • DDeployment > Services > Installation > Setup

How the community answered

(27 responses)
  • A
    11% (3)
  • B
    4% (1)
  • C
    81% (22)
  • D
    4% (1)