A developer is importing a Business Processes (BP) called ftp_CompanyA into production via Resource Manager and Object Updates is set to Yes. What happens if this BP already exists?

The correct answer is C. The import appends a new BP version to the list of previously saved versions, incrementing by. See the full explanation below for the reasoning.

Question

A developer is importing a Business Processes (BP) called ftp_CompanyA into production via Resource Manager and Object Updates is set to Yes. What happens if this BP already exists?

Options

  • AThe BP is not imported.
  • BThe BP gets renamed to ftp_CompanyA_TEMP.
  • CThe import appends a new BP version to the list of previously saved versions, incrementing by
  • DA backup is made of default ftp_CompanyA BP in a file called backup.xml and then it is

How the community answered

(42 responses)
  • A
    12% (5)
  • B
    7% (3)
  • C
    79% (33)
  • D
    2% (1)