Your team uses the agile methodology. At the end of the sprint, your team looks for ways to improve. This process is called:
The correct answer is C. Retrospective. See the full explanation below for the reasoning.
Question
Your team uses the agile methodology. At the end of the sprint, your team looks for ways to improve. This process is called:
Options
- AFail-fast
- BRefactoring
- CRetrospective
- DBacklog
How the community answered
(62 responses)- A6% (4)
- B5% (3)
- C71% (44)
- D18% (11)