This question requires that you evaluate the underlined text to determine if it is correct. The weekly testing status report is part of the project charter. Select the correct answer if the…
The correct answer is C. Project communication plan. See the full explanation below for the reasoning.
Question
This question requires that you evaluate the underlined text to determine if it is correct. The weekly testing status report is part of the project charter. Select the correct answer if the underlined text does not make the statement correct. Select "No change is needed" if the underlined text makes the statement correct.
Options
- ANo change is needed
- BBacklog
- CProject communication plan
- DSprint documents
How the community answered
(27 responses)- A4% (1)
- B4% (1)
- C85% (23)
- D7% (2)