98-379 · Question #1323
What does a sprint task hour burndown chart display?
The correct answer is C. The estimated remaining hours of work for the sprint. See the full explanation below for the reasoning.
Question
What does a sprint task hour burndown chart display?
Options
- AThe actual remaining hours of work for the sprint
- BThe actual hours of work expended for the sprint
- CThe estimated remaining hours of work for the sprint
- DThe estimated hours of work expended for the sprint
How the community answered
(59 responses)- A5% (3)
- B7% (4)
- C75% (44)
- D14% (8)