How many test plans are created in projects that use an agile methodology?

The correct answer is A. One master test plan and one test plan for each sprint. See the full explanation below for the reasoning.

Question

How many test plans are created in projects that use an agile methodology?

Options

  • AOne master test plan and one test plan for each sprint
  • BOne test plan for each sprint
  • COne master test plan
  • DMultiple test plans for each sprint

How the community answered

(44 responses)
  • A
    75% (33)
  • B
    14% (6)
  • C
    5% (2)
  • D
    7% (3)

Community Discussion

No community discussion yet for this question.