Which option is the recommended scope for a work package?

The correct answer is C. one major business capability. See the full explanation below for the reasoning.

Question

Which option is the recommended scope for a work package?

Options

  • Athree business capabilities
  • Bone technical subsystem
  • Cone major business capability
  • Dno recommended size

How the community answered

(42 responses)
  • A
    2% (1)
  • B
    7% (3)
  • C
    79% (33)
  • D
    12% (5)