Which two phases of the TOGAF ADM manage the process of creating a phased roadmap for technology implementation? (Choose two.)

The correct answer is B. Phase E: Opportunities and Solutions C. Phase F: Migration Planning. See the full explanation below for the reasoning.

Question

Which two phases of the TOGAF ADM manage the process of creating a phased roadmap for technology implementation? (Choose two.)

Options

  • APhase D: Technology Architecture
  • BPhase E: Opportunities and Solutions
  • CPhase F: Migration Planning
  • DPhase G: Implementation Governance
  • EPhase H: Architecture Change Management

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    74% (20)
  • D
    4% (1)
  • E
    15% (4)