Cisco
840-425 · Question #34
Which two phases of the TOGAF ADM manage the process of creating a phased roadmap for technology implementation? (Choose two.)
The correct answer is B. Phase E: Opportunities and Solutions C. Phase F: Migration Planning. See the full explanation below for the reasoning.
Question
Which two phases of the TOGAF ADM manage the process of creating a phased roadmap for technology implementation? (Choose two.)
Options
- APhase D: Technology Architecture
- BPhase E: Opportunities and Solutions
- CPhase F: Migration Planning
- DPhase G: Implementation Governance
- EPhase H: Architecture Change Management
How the community answered
(27 responses)- A7% (2)
- B74% (20)
- D4% (1)
- E15% (4)
Community Discussion
No community discussion yet for this question.