840-425 · Question #101
Who are the two primary users of an implementation strategy? (Choose two.)
The correct answer is D. the program leader responsible for achieving business results E. major work package owners. See the full explanation below for the reasoning.
Question
Who are the two primary users of an implementation strategy? (Choose two.)
Options
- Athe technical architect
- Bthe leaders for training
- Cexecutive sponsor and steering committee
- Dthe program leader responsible for achieving business results
- Emajor work package owners
How the community answered
(19 responses)- A5% (1)
- B11% (2)
- C11% (2)
- D74% (14)