Your data import has returned the message that the import has failed. Before trying to import again, which three steps are necessary? (Choose three.)

The correct answer is B. Check the import log fileto identify the problem. C. Reinstall the postgres database. E. Restore the empty cc and c3k databases. See the full explanation below for the reasoning.

Question

Your data import has returned the message that the import has failed. Before trying to import again, which three steps are necessary? (Choose three.)

Options

  • AFix the problem identified in the import log file.
  • BCheck the import log fileto identify the problem.
  • CReinstall the postgres database.
  • DReinstall the IPOCC Server.
  • ERestore the empty cc and c3k databases.

How the community answered

(46 responses)
  • A
    17% (8)
  • B
    76% (35)
  • D
    7% (3)

Community Discussion