You need to identify the primary project management risk inherent in the Contoso sales process improvement project. Which risk should you identify?

The correct answer is A. The integration effort takes longer than the project plan specifies. See the full explanation below for the reasoning.

Question

You need to identify the primary project management risk inherent in the Contoso sales process improvement project. Which risk should you identify?

Options

  • AThe integration effort takes longer than the project plan specifies.
  • BGlobal end-user training is required to support a rapid software deployment.
  • CSoftware is deployed in conjunction with the companys normal hardware lifecycle.
  • DThe IT department increases the scope of the project to include additional requirements.

How the community answered

(33 responses)
  • A
    73% (24)
  • B
    3% (1)
  • C
    15% (5)
  • D
    9% (3)