Question
If the result of an NPV is positive, then the project should be selected. The net present value shows the present value of the project, based on the decisions taken for its selection. What is the net present value equal to?
Options
- ANet profit ?per capita income
- BTotal investment ?Discounted cash
- CAverage profit ?Annual investment
- DInitial investment ?Future value