EC-Council
712-50 · Question #270
712-50 Question #270: Real Exam Question with Answer & Explanation
The correct answer is B. The NPV of the project is negative. See the full explanation below for the reasoning.
Question
Which of the following conditions would be the MOST probable reason for a security project to be rejected by the executive board of an organization?
Options
- AThe Net Present Value (NPV) of the project is positive
- BThe NPV of the project is negative
- CThe Return on Investment (ROI) is larger than 10 months
- DThe ROI is lower than 10 months
Community Discussion
No community discussion yet for this question.