nerdexam
EC-Council

712-50 · Question #259

John is the project manager for a large project in his organization. A new change request has been proposed that will affect several areas of the project. One area of the project change impact is on w

The correct answer is D. Refer to the contract agreement for direction.. See the full explanation below for the reasoning.

Question

John is the project manager for a large project in his organization. A new change request has been proposed that will affect several areas of the project. One area of the project change impact is on work that a vendor has already completed. The vendor is refusing to make the changes as they've already completed the project work they were contracted to do. What can John do in this instance?

Options

  • ARefer the vendor to the Service Level Agreement (SLA) and insist that they make the changes.
  • BReview the Request for Proposal (RFP) for guidance.
  • CWithhold the vendor's payments until the issue is resolved.
  • DRefer to the contract agreement for direction.

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    16% (4)
  • D
    76% (19)

Community Discussion

No community discussion yet for this question.

Full 712-50 Practice