712-50 · Question #259
John is the project manager for a large project in his organization. A new change request has been proposed that will affect several areas of the project. One area of the project change impact is on…
The correct answer is D. Refer to the contract agreement for direction. Option D is correct because when a vendor disputes scope or refuses additional work, the contract is the binding legal document that governs the relationship - it defines the scope of work, change clauses, and obligations for both parties, making it the authoritative first…
Question
John is the project manager for a large project in his organization. A new change request has been proposed that will affect several areas of the project. One area of the project change impact is on work that a vendor has already completed. The vendor is refusing to make the changes as they've already completed the project work they were contracted to do. What can John do in this instance?
Options
- ARefer the vendor to the Service Level Agreement (SLA) and insist that they make the changes.
- BReview the Request for Proposal (RFP) for guidance.
- CWithhold the vendor's payments until the issue is resolved.
- DRefer to the contract agreement for direction.
How the community answered
(25 responses)- A4% (1)
- B4% (1)
- C16% (4)
- D76% (19)
Explanation
Option D is correct because when a vendor disputes scope or refuses additional work, the contract is the binding legal document that governs the relationship - it defines the scope of work, change clauses, and obligations for both parties, making it the authoritative first reference for resolving disputes. Option A is wrong because an SLA governs service performance standards (uptime, response times), not scope of work or change authority - it's the wrong document for this situation. Option B is incorrect because the RFP is a pre-contract solicitation document used to invite bids; once a contract is signed, the RFP is superseded and no longer governs the relationship. Option C is wrong and potentially illegal - withholding payment without contractual basis could expose John's organization to breach of contract liability, making it the most dangerous choice.
Memory tip: Think "Contract = Contract disputes." Whenever a vendor relationship goes sideways, the contract is always the first stop - it's the signed agreement that replaced all prior documents (RFP, proposals, SLAs) as the governing authority.
Topics
Community Discussion
No community discussion yet for this question.