70-243 · Question #72
Your network contains a System Center 2012 Configuration Manager environment. The environment contains a single primary site. The primary site has a distribution point and a management point. You need
The correct answer is B. Install a new management point and configure the management point always to use HTTPS.. You can have one management point that accepts HTTPS client communication and another management point that accepts HTTP client communication. To communicate with a site system role, the client must first locate a site system support the protocol (HTTPS or HTTP) that the client c
Question
Your network contains a System Center 2012 Configuration Manager environment. The environment contains a single primary site. The primary site has a distribution point and a management point. You need to recommend a communication solution that meets the following requirements:
- Communication between the client computers in the research department
and the management point must use HTTPS.
- Communication between all of the other client computers and the
management point must be able to use HTTP.
- Minimize the number of site systems.
What should you do?
Options
- AConfigure the existing management point to use HTTPS.
- BInstall a new management point and configure the management point always to use HTTPS.
- CCreate a new primary child site and configure the site to use native mode.
- DInstall a new management point and configure Windows Firewall to block inbound TCP port 80.
How the community answered
(31 responses)- A26% (8)
- B48% (15)
- C19% (6)
- D6% (2)
Explanation
You can have one management point that accepts HTTPS client communication and another management point that accepts HTTP client communication. To communicate with a site system role, the client must first locate a site system support the protocol (HTTPS or HTTP) that the client can use. By default, clients use the most secure method available to them. Using HTTPS before it communicates with a site system role that uses HTTP. When you deploy a site system role includemanagement points, anApplication Catalog website point, astate migration point, or distribution points, you must specify whether clients connect to the site system by using HTTP or HTTPS. If you use HTTP, you must also consider signing and encryption choices. In a single site, you can have one management point that accepts HTTPS client communication and another management point that accepts HTTP client communication. You can use one site to manage clients across different network locations that use different communication protocols and security settings. uk.co.certification.simulator.questionpool.PList@395c82f9 Other client computers can be configured for Internet and intranet client management. They can automatically switch between Internet-based client management and intranet client management when they detect a change of network. If these clients can find and connect to a management point that is configured for client connections on the intranet, they attempt to connect to an Internet-based management point. Planning for Intrasite Communications in Configuration Manager
Topics
Community Discussion
No community discussion yet for this question.