70-243 · Question #54
Your network contains a System Center 2012 Configuration Manager environment. You create a report that lists compliance information. You schedule the report to run every day at 20:00. You need to…
The correct answer is A. Use snapshots. Creating, Modifying, and Deleting Snapshots in Report History Report history is a collection of report snapshots. You can maintain report history by adding and deleting snapshots, or by modifying properties that affect report history storage. You can create report history…
Question
Your network contains a System Center 2012 Configuration Manager environment. You create a report that lists compliance information. You schedule the report to run every day at 20:00. You need to ensure that on Friday, you can review the results of the report created on the previous Monday. What should you configure the report to do?
Options
- AUse snapshots.
- BUse caching.
- CRender on Friday.
- DUse a shared schedule.
How the community answered
(24 responses)- A88% (21)
- C4% (1)
- D8% (2)
Explanation
Creating, Modifying, and Deleting Snapshots in Report History Report history is a collection of report snapshots. You can maintain report history by adding and deleting snapshots, or by modifying properties that affect report history storage. You can create report history manually or on a schedule. Further information: Cache a Report (Report Manager) One way to improve performance is to configure caching properties for a report. When a report is cached, a copy of the rendered report is saved for a short period of time. The first user who requests the report must wait for all processing to complete before viewing the report. Subsequent users who request the report within the caching period can view it right away because processing has already occurred.