You have a Project Server 2010 environment. Project resources work across multiple locations. You need to associate each resource with its locations. What should you do?

The correct answer is C. Create a custom resource field mapped to a multi-value lookup table. See the full explanation below for the reasoning.

Question

You have a Project Server 2010 environment. Project resources work across multiple locations. You need to associate each resource with its locations. What should you do?

Options

  • ACreate a custom task field mapped to a multi-value lookup table.
  • BCreate a custom project field mapped to a multi-value lookup table.
  • CCreate a custom resource field mapped to a multi-value lookup table.
  • DSynchronize the resource pool with Active Directory.

How the community answered

(30 responses)
  • A
    13% (4)
  • B
    3% (1)
  • C
    80% (24)