You have a Project Server 2010 environment. Project resources work across multiple locations. You need to associate each resource with its locations. What should you do?
The correct answer is C. Create a custom resource field mapped to a multi-value lookup table. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. Project resources work across multiple locations. You need to associate each resource with its locations. What should you do?
Options
- ACreate a custom task field mapped to a multi-value lookup table.
- BCreate a custom project field mapped to a multi-value lookup table.
- CCreate a custom resource field mapped to a multi-value lookup table.
- DSynchronize the resource pool with Active Directory.
How the community answered
(30 responses)- A13% (4)
- B3% (1)
- C80% (24)
- D3% (1)