Microsoft
70-177 · Question #69
You have a Project Server 2010 environment. You need to create a report that displays projects by workflow phase. What should you do?
The correct answer is A. Create a Project Center view. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. You need to create a report that displays projects by workflow phase. What should you do?
Options
- ACreate a Project Center view.
- BCreate a new OLAP cube.
- CCreate a Project view.
- DCreate a new workflow.
How the community answered
(28 responses)- A71% (20)
- B4% (1)
- C11% (3)
- D14% (4)