70-177 · Question #69

You have a Project Server 2010 environment. You need to create a report that displays projects by workflow phase. What should you do?

The correct answer is A. Create a Project Center view. See the full explanation below for the reasoning.

Question

You have a Project Server 2010 environment. You need to create a report that displays projects by workflow phase. What should you do?

Options

  • ACreate a Project Center view.
  • BCreate a new OLAP cube.
  • CCreate a Project view.
  • DCreate a new workflow.

How the community answered

(28 responses)
  • A
    71% (20)
  • B
    4% (1)
  • C
    11% (3)
  • D
    14% (4)