70-177 · Question #67
You have a Project Server 2010 environment. Your company's CIO is performing an audit of the inactive tasks that project managers have in their project plans. However, the CIO cannot access inactive…
The correct answer is B. Select the Include Inactive Tasks check box in the Database Configuration page for the cube. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. Your company's CIO is performing an audit of the inactive tasks that project managers have in their project plans. However, the CIO cannot access inactive tasks in any Data Analysis view. You need to ensure that the company executives can access inactive tasks in the OLAP cube. What should you do?
Options
- AInclude the Flag Status_Task field as a dimension in the cube.
- BSelect the Include Inactive Tasks check box in the Database Configuration page for the cube.
- CSelect the (Select All) check box for Built-in Measures in the Database Configuration page
- DCreate a custom OLAP cube with a custom field named Inactive.
How the community answered
(41 responses)- A10% (4)
- B80% (33)
- C7% (3)
- D2% (1)