The correct answer is A. Assign the Accept Task Update Requests category permission to the Team Leads group. D. Assign the Open Project and Save Project to Project Server category permissions to the. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. You need to configure Project Server so that project managers can assign team leads as approvers for tasks in their projects. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Options
- AAssign the Accept Task Update Requests category permission to the Team Leads group.
- BAssign the Edit Project Summary Fields category permission to the Team Leads group.
- CAssign the Publish Project category permission to the Team Leads group.
- DAssign the Open Project and Save Project to Project Server category permissions to the