You have a Project Server 2010 environment. You need to enable the project manager to allow Resource A to report time for Resource B, while Resource B is on leave. What should you do?

Options

  • AEnable the Manage My Resource Delegates setting for the project manager.
  • BEnable the Manage My Delegates setting for the project manager.
  • CEnable the Can be Delegate setting for the project manager.
  • DEnable the Self-assign team task setting for the project manager.