nerdexam
Microsoft

70-177 · Question #4

You have a Project Server 2010 environment. You need to enable the project manager to allow Resource A to report time for Resource B, while Resource B is on leave. What should you do?

The correct answer is A. Enable the Manage My Resource Delegates setting for the project manager. See the full explanation below for the reasoning.

Question

You have a Project Server 2010 environment. You need to enable the project manager to allow Resource A to report time for Resource B, while Resource B is on leave. What should you do?

Options

  • AEnable the Manage My Resource Delegates setting for the project manager.
  • BEnable the Manage My Delegates setting for the project manager.
  • CEnable the Can be Delegate setting for the project manager.
  • DEnable the Self-assign team task setting for the project manager.

How the community answered

(28 responses)
  • A
    75% (21)
  • B
    14% (4)
  • C
    4% (1)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.

Full 70-177 Practice