Microsoft
70-177 · Question #4
70-177 Question #4: Real Exam Question with Answer & Explanation
Sign in or unlock 70-177 to reveal the answer and full explanation for question #4. The question stem and answer options stay visible for context.
Question
You have a Project Server 2010 environment. You need to enable the project manager to allow Resource A to report time for Resource B, while Resource B is on leave. What should you do?
Options
- AEnable the Manage My Resource Delegates setting for the project manager.
- BEnable the Manage My Delegates setting for the project manager.
- CEnable the Can be Delegate setting for the project manager.
- DEnable the Self-assign team task setting for the project manager.
Unlock 70-177 to see the answer
You've previewed enough free 70-177 questions. Unlock 70-177 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.