You have a Project Server 2010 environment. You need to enable users to view Project Server tasks in Microsoft Outlook. You configure user accounts for Exchange Server synchronization in Project Web…

The correct answer is B. Select Synchronize Tasks in Project Web App (PWA). See the full explanation below for the reasoning.

Question

You have a Project Server 2010 environment. You need to enable users to view Project Server tasks in Microsoft Outlook. You configure user accounts for Exchange Server synchronization in Project Web App (PWA). What should you do next?

Options

  • ASelect Task Alerts options in Project Web App (PWA).
  • BSelect Synchronize Tasks in Project Web App (PWA).
  • CSelect Import Outlook Tasks in Project Professional.
  • DSelect Connect to Outlook in the Project Site.

How the community answered

(18 responses)
  • A
    6% (1)
  • B
    78% (14)
  • C
    6% (1)
  • D
    11% (2)