You have a singleserver Project Server 2010 environment. You are installing a cumulative update on the server. You need to maintain data integrity and ensure that users do not modify project data…
The correct answer is B. Quiesce the farm. See the full explanation below for the reasoning.
Question
You have a singleserver Project Server 2010 environment. You are installing a cumulative update on the server. You need to maintain data integrity and ensure that users do not modify project data during the update process. What should you do first?
Options
- AStop the Project Server Events service.
- BQuiesce the farm.
- CRun the IISReset tool from the command line.
- DRun the Upgrade-SPContentDatabase cmdlet from the SharePoint 2010 Management Shell.
How the community answered
(26 responses)- A12% (3)
- B81% (21)
- C4% (1)
- D4% (1)
Community Discussion