Microsoft
70-177 · Question #19
You have a Project Server 2010 environment. You need to configure a report of active risks and issues across all projects. What should you do?
The correct answer is C. Create a new report in Business Intelligence Center. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. You need to configure a report of active risks and issues across all projects. What should you do?
Options
- AAdd the Risks Web Part to the Project Site.
- BAdd the Issues Web Part to the Project Site.
- CCreate a new report in Business Intelligence Center.
- DCreate a new Project Center view.
How the community answered
(22 responses)- B9% (2)
- C86% (19)
- D5% (1)
Community Discussion
No community discussion yet for this question.