You have a Project Server 2010 environment. You need to configure a report of active risks and issues across all projects. What should you do?

The correct answer is C. Create a new report in Business Intelligence Center. See the full explanation below for the reasoning.

Question

You have a Project Server 2010 environment. You need to configure a report of active risks and issues across all projects. What should you do?

Options

  • AAdd the Risks Web Part to the Project Site.
  • BAdd the Issues Web Part to the Project Site.
  • CCreate a new report in Business Intelligence Center.
  • DCreate a new Project Center view.

How the community answered

(22 responses)
  • B
    9% (2)
  • C
    86% (19)
  • D
    5% (1)