Microsoft
70-177 · Question #14
You have a Project Server 2010 environment. You need to configure a new Visual Reports template based on Microsoft Excel. The template must be available to all current and future projects while they…
The correct answer is D. Create the Visual Reports template in Project Professional and copy it to the enterprise global. See the full explanation below for the reasoning.
Question
You have a Project Server 2010 environment. You need to configure a new Visual Reports template based on Microsoft Excel. The template must be available to all current and future projects while they are connected to Project Server. What should you do?
Options
- ACreate the Visual Reports template in Project Professional and save the project as a template.
- BCreate the Visual Reports template in Project Professional and publish the project.
- CCreate the Visual Reports template in Project Professional and copy it to the Global.mpt file.
- DCreate the Visual Reports template in Project Professional and copy it to the enterprise global
How the community answered
(48 responses)- A2% (1)
- B6% (3)
- C13% (6)
- D79% (38)