You have a Project Server 2010 environment. You create a new enterprise task field. You need to create an aggregated pivot analysis of the new enterprise task field. What should you do?

The correct answer is B. Add the task field to the OLAP cube configuration and build the OLAP cube. See the full explanation below for the reasoning.

Question

You have a Project Server 2010 environment. You create a new enterprise task field. You need to create an aggregated pivot analysis of the new enterprise task field. What should you do?

Options

  • AAdd the task field to a Project view definition and build the OLAP cube.
  • BAdd the task field to the OLAP cube configuration and build the OLAP cube.
  • CCreate a new project details page with the task field.
  • DCreate a lookup table for the task field.

How the community answered

(44 responses)
  • A
    5% (2)
  • B
    70% (31)
  • C
    16% (7)
  • D
    9% (4)

Community Discussion

No community discussion yet for this question.

Full 70-177 Practice