70-158 · Question #88
You use Forefront Identity Manager (FIM) 2010 in your company network. You want to migrate the FIM Portal configuration from the test environment to the production environment. You need to enable…
The correct answer is B. Close Port 5725 in the production environment. D. Disable the FIM Portal in the production environment. F. Stop all Management Agents in the production environment. Enabling maintenance mode in FIM 2010 before migrating portal configuration requires isolating the production environment to prevent data changes during the migration process.
Question
Options
- AClose Port 5725 in the test environment.
- BClose Port 5725 in the production environment.
- CDisable the FIM Portal in the test environment.
- DDisable the FIM Portal in the production environment.
- EStop all Management Agents in the test environment.
- FStop all Management Agents in the production environment.
How the community answered
(53 responses)- A13% (7)
- B75% (40)
- C4% (2)
- E8% (4)
Why each option
Enabling maintenance mode in FIM 2010 before migrating portal configuration requires isolating the production environment to prevent data changes during the migration process.
Closing Port 5725 in the test environment affects the source environment, not the target production environment, and does not protect the production system from changes during migration.
Closing Port 5725 in the production environment blocks inbound SOAP/HTTPS communication to the FIM Service, preventing any new requests from reaching the production FIM Service during migration.
Disabling the FIM Portal in the test environment only prevents access to the source system, but maintenance mode must be applied to the production (destination) environment to protect it during the migration.
Disabling the FIM Portal in the production environment prevents end users and administrators from making configuration or object changes that could conflict with or be overwritten by the incoming migrated configuration.
Stopping Management Agents in the test environment has no effect on the production environment's state and does not prevent production-side synchronization activity from interfering with the migration.
Stopping all Management Agents in the production environment halts synchronization runs that could import or export data changes during the migration window, ensuring a consistent and stable state for the configuration import.
Concept tested: FIM 2010 maintenance mode for portal migration
Source: https://learn.microsoft.com/en-us/microsoft-identity-manager/mim-cm-deploy