Which two of these activities are parts of the phased implementation service component in the implement phase? (Choose two)
The correct answer is C. prepare the site for the system implementation D. install, confgure, integrate and test infrastructure. See the full explanation below for the reasoning.
Question
Which two of these activities are parts of the phased implementation service component in the implement phase? (Choose two)
Options
- Adevelop a staff training program plan
- Bconduct a kickoff meeting
- Cprepare the site for the system implementation
- Dinstall, confgure, integrate and test infrastructure