Which two of these activities are parts of the implementation plan development service component in the design phase? (Chose two)
The correct answer is A. develop an implementation schedule B. discuss project roles and responsibilities. See the full explanation below for the reasoning.
Question
Which two of these activities are parts of the implementation plan development service component in the design phase? (Chose two)
Options
- Adevelop an implementation schedule
- Bdiscuss project roles and responsibilities
- Cconfirm project and milestone dates
- Dcreate a detailed staff training matrix
- Ecreate a site-specific network implementation plan
How the community answered
(31 responses)- A81% (25)
- C6% (2)
- D3% (1)
- E10% (3)