nerdexam
Cisco

650-059 · Question #31

Conducting a project kick-off in the plan phase provides which of the following customer benefits? Select exactly 1 answer(s) from the following:

The correct answer is D. confirm project roles and responsibilities, as well as milestone dates. See the full explanation below for the reasoning.

Question

Conducting a project kick-off in the plan phase provides which of the following customer benefits? Select exactly 1 answer(s) from the following:

Options

  • Aensure that it receives detailed network diagrams
  • Breduce the risk of downtime due to facilities-related problems
  • Censure end-user support immediately after the launch of a new system
  • Dconfirm project roles and responsibilities, as well as milestone dates

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    83% (25)

Community Discussion

No community discussion yet for this question.

Full 650-059 Practice