The correct answer is D. confirm project roles and responsibilities, as well as milestone dates. See the full explanation below for the reasoning.
Question
Conducting a project kick-off in the plan phase provides which of the following customer benefits? Select exactly 1 answer(s) from the following:
Options
- Aensure that it receives detailed network diagrams
- Breduce the risk of downtime due to facilities-related problems
- Censure end-user support immediately after the launch of a new system
- Dconfirm project roles and responsibilities, as well as milestone dates