In wich service component in the design phase would you provide a site-specific system implementation plan which defines the activities, configraions, and commissioning test plans required to implemen

The correct answer is E. implementation plan development. See the full explanation below for the reasoning.

Question

In wich service component in the design phase would you provide a site-specific system implementation plan which defines the activities, configraions, and commissioning test plans required to implement routing and switching solution components and software?

Options

  • Astaging plan development
  • Bdetailed design development
  • Cproject kick-off
  • Dsystems acceptance test plan development
  • Eimplementation plan development

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    11% (4)
  • C
    6% (2)
  • D
    3% (1)
  • E
    78% (28)

Community Discussion

No community discussion yet for this question.